- New HVAC equipment was lifted onto the kichen and hall! Yea!
- Interior painting for the main hall mostly complete! Yea!
- High Power Line conduit is in and city electriclal vault work is complete! Yea!
- The water main issue caused us to do some ad hoc repairs and changes to the layout. While they are good, we have to document them in our prints and submit them to the city before additional inpsections can occur - obviously delaying some items (that is why we still have holes on the side of the kitchen). This will delay our ability to use the hall until at least Labor Day. Sigh.
- We did make some progress with the city on a thorny issue on the Sanctuary addition. While we do not have full approval yet, we are narrowing down the questions to fairly minor issues.