The 1-minute read:

This has been a very … interesting few weeks as we tackled a lot of work inside the hall but had a couple setbacks elsewhere.  However, as of today, 8/7, we seem to have good head of steam and are moving forward again.

  • Water Restored! The final fix is in place and ready for inspection next week.
  • The Grease Interceptor for kitchen waste water is installed and inspection is scheduled for next week.
  • Big electrical inspections are scheduled for next week, allowing us to start closing the trenches.
  • Kitchen A/C ducting is being put in place. Prep for epoxy flooring is coming up
  • Hall is cleaned up for painting next week. A primer coat is on the walls now.
  • Sanctuary Addition/Children’s Wing Remodel/Bathrooms – we are still working with the city of Anaheim Planning department on questions that have come up. We do not yet have an estimated start date for this project, but the questions are getting fewer.